Before processing the steel structure, the construction personnel shall prepare the process regulations and the chief engineer shall approve them. Carefully inspect the process preparation of each process, and prepare and mutually review the processing drawings.
one point two
Inspect various materials and tools required for processing, and ensure that the process equipment meets the requirements of the process regulations.
one point three
Construction personnel shall carry out technical disclosure work for each process in advance.
one point four
Provide training and assessment in advance for operators on duty, confirm the qualifications for special types of work, and hold certificates to work.
one point five
Before setting out, the processing drawings should be checked and the process requirements mastered, and any problems found should be promptly reported to the relevant departments.
Point 2
Steel component layout
two point one
During the laying out process of steel components, it is necessary to verify the quantity, material specifications, models, dimensions, etc. of the steel structure and connectors, and then carry out batching, marking and laying out, and sorting and stacking.
two point two
The important node dimensions of the structure or component in the machining drawing can be sampled or calculated for verification.
two point three
Before material marking, the steel specifications, materials, and batch numbers must be checked, and the surface of the steel must be cleaned of dirt such as oil and soil.
The third point
cutting
three point one
After setting out the profile steel flange plate, web plate, and end plate, use a CG1-100 semi-automatic cutting machine to cut to avoid the phenomenon of uneven edges, missing edges, and broken corners of steel components; Rib plates and rigid support connecting plates are cut using a shearing machine; The profiles are cut manually or with a grinder.
three point two
Before cutting, the surface of the steel should be cleaned of rust, oil stains, etc.
three point three
Plate gas cutting should be carried out on a dedicated platform.
Fourth point
Drilling
four point one
The connection between steel components and connectors is connected with high-strength bolts. The position and size of the aperture require precision and high accuracy. Use a drilling machine to drill holes.
four point two
When drilling, use a drilling jig and a laminated plate sleeve drill, and fix the hole with a fixture to prevent the drilling jig or the laminated plate from being misaligned.
four point three
After the drilling is completed, a polishing machine should be used to thoroughly clean the bottom and remove burrs from the hole edges, without damaging the base material.
Point 5
assemble
five point one
Before assembly, the parts should be corrected, and thicker steel plates can be corrected using a press or flame heating.
five point two
The components are corrected using a flange straightening machine to correct the beams produced.
five point three
The reasonable assembly sequence of components should be determined based on their structural form, welding and connection methods, and welding and connection sequence. To reduce welding and joint deformation.
five point four
The steel columns and beams of this project are all solidly sampled on a steel platform in a 1:1 ratio, and all parts are assembled according to the processing drawings.
Point 6
Welding and connection
six point one
general requirements
Welders must hold a certificate to work.
Welding rods and fluxes should be baked according to the baking temperature specified in the technical manual before use,.
Before welding, the welder should recheck the quality of the component joints and the location of the welding area
Scan for more information
Address: 3678 Xinhua Road, Tianjin Pilot Free Trade Zone (Central Business District)
Unit 1002, 10th Floor, Baofeng Building (New Financial Building)
Website: www.jinxilvjian.com
Popular search: American standard H-beam, British standard H-beam, European standard H-beam